I've got a quick update regarding the progress of the 4 required "Steps" that were outlined earlier this week.
Step 1. Riley County Parks has started the process of getting the underground utilities located & marked. However, it may take the locate company(s) until next Wednesday (24th) to get all of them marked. If the timing plays out that way (at best), that would only allow Thursday & Friday of next week to get Steps 2 & 3 completed.
Steps 2 & 3 Reminder:
2. Us adjusting our pin placements based on the utilities they find.
3. Riley County Parks getting a bobcat dispatched to Fairmont Park and drilling holes for all of our new & adjusted pin placements.
With that in mind, there's a pretty good chance that our first workday may not be until Aug. 3rd & 4th. However it's still too early to tell. I will post updated info as soon as possible.
Good News:
At this point in time, I believe Step #4 (obtaining the concrete & irrigation boxes) will not be a problem. I've been told that should be on-hand by next week.
Thanks again,
Rick Petrie
P.S. Please bare with me. The schedule for the next few weeks is going to be very fluid & hectic, but well worth it.
For those of you who have not read the above News, I'll paraphrase. It's still too early to know if our pin placement install workdays are two or three weeks away. We should know for sure by Wednesday.